Notice: This page requires JavaScript to function properly.
Please enable JavaScript in your browser settings or update your browser.
Apprendre Challenge: Task Scheduling Script | Project Management and Optimization
Practice
Projects
Quizzes & Challenges
Quizzes
Challenges
/
Python for Civil Engineers

bookChallenge: Task Scheduling Script

Project scheduling is a foundational aspect of civil engineering project management. By clearly defining tasks, durations, and dependencies, you can ensure that projects progress efficiently and avoid costly delays. Automated scheduling tools help transform complex task lists into actionable timelines, reducing manual errors and improving clarity for all stakeholders. Understanding how to compute earliest start and finish times for each task, given their dependencies, forms the backbone of effective project planning. This approach not only streamlines communication but also provides a solid basis for resource allocation, risk management, and progress tracking.

Tâche

Swipe to start coding

Write a function that, given a list of tasks with durations and dependencies, computes the earliest start and finish times for each task and outputs a formatted schedule table.

  • Each task is represented by a dictionary with keys 'name', 'duration', and 'dependencies'.
  • The function must determine the earliest possible start time for each task, considering that all dependencies must be completed first.
  • The function must calculate the earliest finish time for each task as its start time plus its duration.
  • The function must output a schedule table containing each task's name, start time, and finish time.

Solution

Tout était clair ?

Comment pouvons-nous l'améliorer ?

Merci pour vos commentaires !

Section 3. Chapitre 3
single

single

Demandez à l'IA

expand

Demandez à l'IA

ChatGPT

Posez n'importe quelle question ou essayez l'une des questions suggérées pour commencer notre discussion

close

bookChallenge: Task Scheduling Script

Glissez pour afficher le menu

Project scheduling is a foundational aspect of civil engineering project management. By clearly defining tasks, durations, and dependencies, you can ensure that projects progress efficiently and avoid costly delays. Automated scheduling tools help transform complex task lists into actionable timelines, reducing manual errors and improving clarity for all stakeholders. Understanding how to compute earliest start and finish times for each task, given their dependencies, forms the backbone of effective project planning. This approach not only streamlines communication but also provides a solid basis for resource allocation, risk management, and progress tracking.

Tâche

Swipe to start coding

Write a function that, given a list of tasks with durations and dependencies, computes the earliest start and finish times for each task and outputs a formatted schedule table.

  • Each task is represented by a dictionary with keys 'name', 'duration', and 'dependencies'.
  • The function must determine the earliest possible start time for each task, considering that all dependencies must be completed first.
  • The function must calculate the earliest finish time for each task as its start time plus its duration.
  • The function must output a schedule table containing each task's name, start time, and finish time.

Solution

Switch to desktopPassez à un bureau pour une pratique réelleContinuez d'où vous êtes en utilisant l'une des options ci-dessous
Tout était clair ?

Comment pouvons-nous l'améliorer ?

Merci pour vos commentaires !

Section 3. Chapitre 3
single

single

some-alt